Case Study

Agency Approvals Float Oil Rig Fast

Agency Approvals Float Oil Rig Fast

Pages 1 Pages

Agency Approvals Float Oil Rig Fast Problem: A new off-shore drilling rig was sitting in port waiting for a combination water injection/oil separation system before it could be towed out to the drilling site. Every day that passed was costing the customer tens of thousands of dollars. This system is used in two phases; first to heat salt water for injecting into the well to improve the oil's pumpability, and, second, to assist in the water/crude oil separation process. A big obstacle was the required CSA approval on the heaters and control panels. Normally this process can take up to six months. Solution: Watlow was able to get the American Bureau of Shipping (ABS) to witness the heater hydro-testing and get a special exemption. This dramatically shortened the approval process down to thre