Case Study

AECC Aberdeen - Henry Boot Developments

AECC Aberdeen - Henry Boot Developments

AECC Aberdeen Henry Boot Developments CASE STUDY grounddevelopments.co.uk Principal Contractor Robertson Construction Group On-site July 2016 – July 2017 Development Area 380,000m 2 Topsoil Strip 160,000m 3 Cut-to-Fill 470,000m 3 Works • Topsoil Strip • Remediation • Stabilised Earthworks PROJECT DESCRIPTION The new £330 million Aberdeen Exhibition Conference Centre (AECC) development is located south of Aberdeen airport. It was formerly the