1201 Main Street • Suite 2360 Columbia, SC 29201 803.779.3025 redrockdevelopments.com Specs Case Study Advanced Drainage Systems, a large manufacturer of HDPE pipe, required a new manufacturing location to serve the Carolinas market. The requirement was for a 20-acre, rail- served site. Ultimately, the site selected required complete coordination of a road extension and rail spur to meet production schedule. • assessed all available sites in search area, • coordinated contractor selection and preliminary design, • provided incentive analysis and negotiated final incentives • coordinated rail spur implementation and site work The project was completed on time and ADS was so pleased they now use this project as a model facility. The project was developed or constructed by principals of