Case Study

50kW installation, Riding School, Hampshire

50kW installation, Riding School, Hampshire

Pages 2 Pages

50kW installation, Riding School, Hampshire The 50 kilowatt array consisted of 192 modules and was positioned on the east- southeast facing roof face of the building. There was a plant room within the barn that housed the connection point and as such it was not be necessary to trench any cables into the ground. The inverters were fixed to the wall of the store at high level, and the AC connection was made within the building. During the design process it was necessary to consider shading from each of the four towers and careful modelling ensured that no panels were placed within the shaded areas. The shade risk was further mitigated through the use of Solar Edge optimisation and inverters.In addition to the shade mitigation, we chose Solar Edge as a product for fire safety on this projec