Case Study
3 ARENA CENTRAL - WORK IN PROGRESS
PROJECT NAME: 3 Arena Central CLIENT: ADSCL LOCATION: Birmingham M&E ORDER VALUE: £17m CONTRACTOR: Galliford Try M&E DESIGN AND BUILD: Dodd Group Dodd Group, based on the success of Project 2 Arena Central (HSBC Bank), negotiated and secured this 14 floor Office Block, which will offer 230,000 sq ft of commercial space. Dodd Group and Design Partners, Capita have taken the design from BSRIA Stage 2 through to BSRIA Stage 5, developing a BIM model to Level 2. Dodd Group and Capita have recently completed the Design to BSRIA 4C and presented to the tenant, HMRC, for approval. The design has been completed in line with the agreed Cost Plan. The project is due to be handed over for Fit Out in early 2020. 3 ARENA CENTRAL - WORK IN PROGRESS doddgroup.com | Dodd Group, Stafford Park 13, Telford