Case Study

158,000 Pound Transformer

158,000 Pound Transformer

Pages 1 Pages

OMEGA MORGAN. COM PORTLAND (503) 647-7 47 4 SEA TTLE (253) 825-7500 CALGARY (855) 588-3230 PROJECT: 158,000 POUND TRANSFORMER INDUSTRY: Public Utilities PROJECT TYPE: Specialized Heavy Rigging & Transportation PROJECT OVERVIEW: Omega Morgan supported the Wildish Building Company when they took on a project to up- grade an existing powerhouse. Wildish Building Company need- ed to remove two transformers and then install two new larger transformers. The project also re- quired the removal and replace- ment of a powerhouse deck, and, in order to comply with the limited deck loading, Omega Morgan had to design and build a runway to distribute a 158,000 pound transformer and slide gear system load to 500 PSF . EQUIPMENT USED: 20K warehouse forklif