11th Street Bridge Project

11th Street Bridge Project

Pages 1 Pages

11th Street Bridge Project Washington, D.C. Alternative delivery method and innovative procurement deliver DDOT’s largest highway project under budget and ahead of schedule • Alternative delivery method saves approximately $80 million • Innovative procurement cuts schedule by five years • Overall budget reduced by $500,000 without sacrificing quality When the cost to replace two spans with three bridges was deemed unaffordable, program manager HNTB presented the Department of the District of Columbia with new plan to replace and widen the 11th Street Bridges above the water line and build a third bridge for local traffic. HNTB began with a day-long success management workshop, which generated agreement among 40 stakeholders on five program goals. To foster innovation and flexibility, the f