Case Study
1-in-3 Temporary Roadway
1-in-3 Temporary Roadway Last Winter incurred the worst rainfall on record and Story Contracting were keen to source a fail-safe product for an embankment re-grade on Network Rail's west coast mainline.Customer Name Story Contracting Products Used Lion Panel LION has spent many years conducting emergency works as well as planned maintenance operations such as this land slip repair. Ian Burney, one of our railaccess experts set to work engineering a solution for the project. The 18 week, re- grade project was required over the winter period and had to guarantee the access and transportation of 20,000 tons of stone to re-grade 385 metres of embankment, together with the safe access of all plant and personnel. Ian and his crew installed a 2km temporary roadway across the scenic landscape in C